Monthly monitoring report and payment forecasting

Monthly monitoring reports inform us of the progress of your project, the key risks and the forecasted payment claims in a standardised format. 

Each grant recipient will receive a monthly monitoring report (MMR) template tailored to your project and should be in contact with a dedicated relationship manager to support the delivery of the project. In addition to regular calls and emails with your relationship manager, we ask that a monthly monitoring report is submitted for each Phase 2 Scotland’s Public Sector Heat Decarbonisation Fund project. 

The MMR includes guidance on how it should be completed. Each MMR requires recipients to complete four steps, located in separate tabs within the excel document. Please ensure all steps are up to date before submitting the report.

  • Step 1: measure progress
  • Step 2: report
  • Step 2.5: conditions
  • Step 3: project programme forecast

We require the report to be updated and submitted by email to your Salix relationship manager no later than COP on the 15th of each calendar month. If the 15th falls on a bank holiday or weekend, we ask you provide it to your relationship manager the working day before the 15th (see full submission schedule below).

Reporting period Latest date to submit the monthly monitoring report
1 Jul 2025 to 31 Jul 2025 Fri 15 Aug 2025
1 Aug 2025 to 31 Aug 2025 Mon 15 Sep 2025
1 Sep 2025 to 30 Sep 2025 Wed 15 Oct 2025
1 Oct 2025 to 31 Oct 2025 Fri 14 Nov 2025
1 Nov 2025 to 30 Nov 2025 Mon 15 Dec 2025
1 Dec 2025 to 31 Dec 2025 Thur 15 Jan 2026
1 Jan 2026 to 31 Jan 2026 Fri 13 Feb 2026
1 Feb 2026 to 28 Feb 2026 Fri 13 Mar 2026

Payment forecasting

Within each monthly monitoring report (MMR), we require grant recipients to provide us with an accurate forecast of payment requests.

Your Phase 2 Scotland’s Public Sector Heat Decarbonisation Fund grant can only be drawn down on an evidence-of-need basis, this means that works should have been completed on-site and have been invoiced for before making a payment claim. You cannot draw down the grant award in advance of incurring costs or works taking place on-site. 

Therefore, when submitting your MMR forecast, please only forecast claims where you are confident you will have invoices by the claim submission deadline (please see payment process for full schedule).

There is no requirement to add a forecast in each month. Inaccurate forecasting may impact our ability to make payments to you.

The total forecast across the projects term should add up to the grant allocation, unless you have an underspend which you must notify your Salix relationship manager of.

Any questions

Please see the ‘frequently asked questions’ webpage or ask your relationship manager for support. 